Oracle has sent a force majeure notice to the developer of Project Jupiter, the AI data center campus it intends to occupy in Doña Ana County, New Mexico, Bloomberg reports, citing people familiar with the situation. The recipient is a unit of Blue Owl Capital. Per Bloomberg's account, Oracle is not trying to walk away as the site's main tenant; it is trying to put off payments should the campus fail to come online in 2028 as planned.
Force majeure is French for "superior force," and it is the clause in a contract that lets one party press pause on its obligations when something outside its control gets in the way. Think of it as the fine print on a concert ticket that covers the hurricane, moved into a multibillion-dollar lease. A notice does not end the deal. It puts the other side on record that the clock may have to stop. TechCrunch reports the clause is common in energy and commodities contracts.
Both companies answered on the record, and neither disputed that the notice exists. "Project Jupiter remains on our planned schedule," Oracle said in a statement to CNBC. "We are fully committed to New Mexico and confident in our path forward." The developer's parent was equally brief. "This notice does not change the financial commitments to this multi-year project," Blue Owl Capital said in a statement to CNBC, which also confirmed the notice went to the Blue Owl unit.
What sits between those two statements is a schedule Oracle says is intact and a clause that exists for the case where it is not. In April, Oracle and BorderPlex Digital Assets said Project Jupiter would run entirely on Bloom Energy fuel cells, up to 2.45 gigawatts of installed capacity, replacing the gas turbines and diesel generators in the earlier plan. That is roughly the output of two large nuclear reactors, delivered by boxes that make electricity from gas through chemistry rather than by burning it, and Oracle's July letter to the New Mexico Environment Department says the gas will be natural gas.
Natural gas needs a pipe. TechCrunch reports the Energy Transfer pipeline meant to feed the site has been pushed back nearly six months, to February 1, 2027, after regulators repeatedly denied permits for the route, and that a separate air-quality permit for the fuel cell system is still pending, with the state environment department facing a November 23 deadline to decide. The logic of the notice writes itself: no permit, no pipe; no pipe, no gas; no gas, no 2.45 gigawatts; no power, no 2028.
Keep the tenant framing straight, too. Oracle's letter to the state describes the company as the tenant of the campus and commits it to paying all of the project's energy costs. The building is the developer's, which is why the notice runs from Oracle to Blue Owl's unit and not the other way around. If the power plant is late, who carries the cost of an empty campus is a landlord-and-tenant question, and this is Oracle getting its answer on file early.
CNBC reports that co-CEO Clay Magouyrk told analysts on the company's September 10 earnings call that Project Jupiter would not affect its fiscal 2027 revenue or earnings guidance. Per TechCrunch, the campus is one of the flagship sites of Stargate, the AI infrastructure program Oracle, OpenAI and SoftBank announced with President Donald Trump, and it has drawn opposition from residents and environmental groups. The two dates to watch are now November 23 and February 1, because there is a contract clause sitting behind each of them.