Non-Profit Ties 60% of Anthropic’s Mapped US Data Center Power Demand to Natural Gas

The Better Data Center Project mapped 19 US sites: about 26% on-site gas, the rest grid power at the national 47% gas mix. Anthropic says gas comes online fast.

Non-Profit Ties 60% of Anthropic's Mapped US Data Center Power Demand to Natural Gas

Data centers that serve Anthropic‘s Claude models largely run on natural gas, according to research from the Better Data Center Project, a US non-profit that advocates for communities near fast-growing AI sites. Data Center Dynamics reported the findings on Nov. 19, along with Anthropic’s response.

The headline figure is 60 percent, and the way it is built matters as much as the number.

The non-profit mapped 19 US sites where, by its count, Anthropic has leased between 5.9 and 9.6 GW of capacity, out of roughly 15 GW the company has contracted. Of those mapped sites, it says about 2.5 GW, or 26 percent, is powered by on-site natural gas. The rest draws on the grid. The non-profit then applies the US grid’s overall mix, which it puts at 47 percent natural gas, to that grid-tied share. Twenty-six percent on-site gas plus 47 percent of the remaining 74 percent comes to about 60 percent.

For a facilities engineer, two things follow from that arithmetic. First, the grid portion uses a national average, not the generation mix of the regions where these sites actually connect, and the gas share differs from one regional grid to another. Second, the base is the mapped capacity, which by the group’s own range is well under the 15 GW total.

The estimate’s limits were spelled out in the same report by Paweł Czyżak, chief executive and founder of Ornaq. “To be fair, these are estimates. Anthropic doesn’t disclose its sites, at least 5GW isn’t mapped, and some attributions are speculative,” he said, adding that Anthropic is not the only AI company running on gas.

Anthropic’s response addressed the gas directly. A spokesperson told Data Center Dynamics the company is adding new generation so its data centers do not draw on supply used by local homes and businesses. “Much of that new power is natural gas, which can be brought online quickly, ramps up and down as demand changes, and is abundant in the places we’re considering for data centers,” the spokesperson said, adding that Anthropic is also working to broaden its mix with geothermal, wind, solar and emerging technologies, and is designing renewable-powered projects in regions with strong renewable resources.

The on-site gas is not hypothetical. Earlier this month Anthropic agreed a $3.4 billion deal for 1.7 GW of natural gas generators from Caterpillar, with OnePWR as partner, for use at its data centers within about two years, Data Center Dynamics reports. The company also pointed to its membership in the carbon buying consortium Frontier and its work with the emissions accounting platform Watershed.

Anthropic has company in this. Microsoft, Meta, Amazon and Google have all signed deals for large on-site gas generators in the US, largely to get around multi-year waits for a firm grid connection.

For enterprises that report the emissions of the AI services they buy, the useful next step is site-level data: which locations, how many megawatts each, and what actually supplies them. The 60 percent figure is an estimate with stated gaps. A disclosed site list would turn it into a number buyers could check.