Army Picks Carlyle and CyrusOne to Build AI Data Centers on Two Bases

The conditional selection opens exclusive lease talks over about 1,384 acres at Fort Bliss and roughly 1,201 acres at Dugway Proving Ground. No capacity figure, no dollar value and no signed lease yet.

Army Picks Carlyle and CyrusOne to Build AI Data Centers on Two Bases

The Army holds a great deal of land it is not permitted to sell and does not currently need, and it has decided to put commercial AI data centers on two pieces of it. CyrusOne has been conditionally selected for a site of roughly 1,201 acres at Dugway Proving Ground in Utah, and the investment firm Carlyle for about 1,384 acres at Fort Bliss in Texas.

Conditionally is doing real work in that sentence. What the service announced is the right to talk, exclusively, about terms. Both firms now enter a negotiation period meant to settle a lease, and the Army says plainly that the deal is not yet final.

The legal machinery is an Enhanced Use Lease, which sounds like paperwork and is the genuinely interesting part. Title 10 of the U.S. Code, section 2667, lets a military department lease property it still holds on its books but does not fully use. Picture a family that cannot sell the far end of the farm, so it rents the field to someone who will build a barn there and eventually hand the barn back.

Money flows in one direction at the start. Carlyle and CyrusOne would be responsible for financing, building, operating, maintaining and decommissioning the facilities, on what the Army describes as underutilized but non-excess land, at no upfront cost to taxpayers. The two were chosen through what the service calls a rigorous and competitive process.

Timing is where the sites part company. Initial Operating Capability, which the military pronounces letter by letter as I-O-C, is projected for fiscal 2027 at Fort Bliss and fiscal 2029 at Dugway. IOC is the point at which the first useful slice of a facility starts doing its job rather than the point at which the last wall goes up, which is why it can land years before anyone would call a campus finished.

Handling the lease negotiations and the technical work, environmental review included, is the U.S. Army Corps of Engineers. On sites this size, in a Texas border county and a Utah desert range, review timelines and water questions tend to set the schedule more reliably than construction does.

Here is the part an infrastructure reader will notice first. The announcement put no megawatt figure on either site, no dollar value, no lease length, and no job count beyond a projection of a significant number of American jobs. Capacity is the number that separates a serious build from a land option, and on 26 March it was not in the release.

Carlyle is a private equity firm rather than a data center operator, and CyrusOne is a portfolio company jointly held by funds managed by KKR and BlackRock. Read the two selections together and the Army has invited several of the largest pools of infrastructure capital anywhere to underwrite compute on its own installations, which is a very different arrangement from buying servers.

The service frames the effort as aligned with the White House's 2025 executive order on accelerating federal permitting of data center infrastructure, and says the initiative would enhance computational capability for the warfighter. Should the leases be signed on the terms described, the Army would end up as landlord to buildings it does not own, on ground it cannot sell, running workloads it has not yet described.